WET Prototype Validation
You will check all the claims: (1)
losslessly, (2) traversing metal &
water, and (3) beyond the near-
>eld.
3
Test Energy-Grid Segment
You will select an energy-grid
segment to deploy a real-life test
of TWD's WET-grid and give TWD
its speci>cations.
34
WET-Grid Manufacturing
TWD will build and test the
quality of the antennas to make
sure they >t the requirements of
the WET-Grid.
34
WET-Grid Engineering
TWD will calculate antennas
requirements (using the location
and size of the energy-grid
segment & the type of current).
WET-Grid Test
TWD will supervise the transport
and installation of the antennas
on the energy-grid segment, and
test the WET-grid.
WET-Grid Validation
You will validate the proper
delivery and functioning of the
WET-Grid segment.
WET-Grid Deployments
You will exercise the TWD
distribution agreement to
progressively deploy the WET-
Grid technology on more sites.
Total Costs (CHF): 3 – 5 millions
Total Duration: 11 – 19 months
Next Step
WET-IoT with
remote power
fetched from
WET-Grids.
Uncertainties: (1) regulation, (2) energy industry cooperation,
(3) third-parties' execution.
WET-Grid Use-Case Roadmap